Mine Closure Guidelines–2025

 

Multiple Choice Questions (Mine Closure Guidelines–2025)

1. The Mine Closure Plan forms an integral part of:

A. Environmental Clearance
B. Forest Clearance
✔ C. Mining Plan
D. Mining Lease


2. Mine Closure consists of:

A. Final Closure only
B. Temporary Closure only
✔ C. Progressive and Final Mine Closure
D. Abandonment only


3. Progressive Mine Closure activities are carried out:

A. Only after mine closure
✔ B. Throughout the life of the mine
C. After EC
D. After FC


4. Final Mine Closure activities generally commence:

A. Before mining starts
B. During exploration
✔ C. Towards the end of mine life
D. During land acquisition


5. Escrow Account is opened in:

A. Reserve Bank of India
✔ B. Scheduled Bank
C. State Treasury
D. District Collector Office


6. Escrow Account is maintained in consultation with:

A. DGMS
✔ B. Coal Controller Organisation (CCO)
C. IBM
D. CPCB


7. Escrow funds are meant exclusively for:

A. Coal production
B. Machinery purchase
✔ C. Mine Closure activities
D. Land acquisition


8. Base Escrow Rate for Opencast Mines is:

A. ₹10 lakh/ha
B. ₹12 lakh/ha
✔ C. ₹14 lakh/ha
D. ₹20 lakh/ha


9. Base Escrow Rate for Underground Mines is:

A. ₹1 lakh/ha
✔ B. ₹2 lakh/ha
C. ₹5 lakh/ha
D. ₹10 lakh/ha


10. Escrow rates are escalated using:

A. CPI
✔ B. WPI
C. GDP
D. Inflation Index


11. Escrow amount is deposited every:

A. Quarter
B. Month
✔ C. Financial Year
D. Five Years


12. Annual Escrow deposit should be made before:

A. 31 March
B. 30 June
✔ C. 30 September
D. 31 December


13. Interest for delayed Escrow deposit is:

A. 0.5% per month
✔ B. 1% per month
C. 5% per annum
D. 10% per annum


14. Annual Escrow deposits are compounded at:

A. 2%
B. 3%
C. 4%
✔ D. 5%


15. Maximum yearly reimbursement is:

A. 100%
B. 75%
✔ C. 50% of previous year's deposited amount
D. 25%


16. Reimbursement is based on:

A. Production
B. Coal Dispatch
✔ C. Actual Mine Closure Work
D. Profit


17. Which document is mandatory for reimbursement?

A. DGMS Certificate
✔ B. Cost Certificate by Certified Auditor
C. Pollution Certificate
D. Railway Receipt


18. Which certification is also required?

A. Collector Certificate
B. IBM Certificate
✔ C. Self-Certification of Work Done
D. Panchayat Certificate


19. For Opencast mines reimbursement also requires:

A. Drone License
✔ B. Geo-referenced Satellite Image/Drone Survey
C. EC Copy
D. Lease Deed


20. Annual reimbursement claim should be submitted by:

A. 30 June
B. 31 July
✔ C. 30 September
D. 31 December


21. CCO releases reimbursement by:

A. 30 September
B. 30 October
C. 30 November
✔ D. 31 December


22. Progressive Mine Closure status is reviewed every:

A. Year
B. Two years
✔ C. Five years
D. Ten years


23. Five-year closure activities are subjected to:

A. Internal Audit
✔ B. Third Party Monitoring
C. DGMS Inspection
D. Police Verification


24. Minimum percentage of five-year Escrow amount for Community Development is:

A. 10%
B. 15%
C. 20%
✔ D. 25%


25. Community Development activities mainly include:

A. Coal production
B. Machinery purchase
✔ C. Skill Development & Livelihood
D. Mine Survey


26. Claim under one activity should not exceed:

A. Half of Escrow
✔ B. One-third of five-year earmarked amount
C. Entire Escrow
D. 10%


27. Which is a reimbursable activity?

A. Coal transportation
✔ B. Plantation
C. Explosive purchase
D. Coal washing


28. Which is eligible for reimbursement?

A. HEMM purchase
B. Mine development
✔ C. Biological reclamation
D. Drilling


29. Which activity is reimbursable?

A. Coal extraction
B. Hiring Dumper
✔ C. Landscaping
D. Explosives


30. Which activity qualifies?

A. Crusher installation
B. CHP Construction
✔ C. Topsoil Spreading
D. Railway siding


31. Which activity qualifies?

A. Coal loading
✔ B. Rehabilitation of OB Dumps
C. Coal sampling
D. Conveyor installation


32. Which activity qualifies?

A. Production enhancement
B. Drilling
✔ C. Site Cleaning
D. Blasting


33. Which activity qualifies?

A. Mining Machinery Purchase
✔ B. Dismantling Structures
C. Mine Expansion
D. Bench Formation


34. Which is reimbursable?

A. Coal dispatch
✔ B. Boundary Wall/Fencing
C. Crusher
D. Railway


35. Which is reimbursable?

A. HEMM overhaul
✔ B. Environmental Monitoring
C. Coal Handling
D. Mine Opening


36. Which activity qualifies?

A. Coal Stocking
✔ B. Air & Water Quality Monitoring
C. Wagon Loading
D. Coal Crushing


37. Post Closure Monitoring period is:

A. One year
✔ B. Two years
C. Three years
D. Five years


38. Post Mining Closure period is:

A. One year
B. Two years
✔ C. Three years
D. Five years


39. Combined closure period shall not exceed:

A. Five years
B. Six years
✔ C. Seven years
D. Eight years


40. Final Mine Closure Plan is submitted:

A. At Mine Opening
B. During Exploration
✔ C. Five years before intended closure
D. After abandonment


41. Mine Closure Certificate is issued by:

A. DGMS
B. IBM
✔ C. Coal Controller
D. CPCB


42. Final Mine Closure requires:

A. Internal Audit only
✔ B. Third Party Audit
C. Safety Audit only
D. Financial Audit only


43. Remaining balance after post-closure monitoring released is:

A. 50%
B. 75%
✔ C. 90%
D. 100%


44. Remaining balance retained is:

A. 2%
B. 5%
✔ C. 10%
D. 20%


45. The retained 10% fund is meant for:

A. Coal Production
✔ B. Just Transformation
C. Machinery
D. Drilling


46. Just Transformation mainly supports:

A. Mine Expansion
B. Coal Transport
✔ C. Skill Development & Employment
D. Coal Dispatch


47. Failure to deposit Escrow may result in:

A. Appreciation
B. Bonus
✔ C. Withdrawal of Mine Opening Permission
D. Production increase


48. If Mine Closure activities deviate from approved plan, penalty may be:

A. 5%
B. 10%
✔ C. Up to 20% of annual Escrow amount
D. 50%


49. The primary responsibility for Mine Closure lies with:

A. Coal Controller
B. State Government
✔ C. Mine Owner
D. District Collector


50. The purpose of Escrow Account is:

A. Increase production
B. Machinery procurement
✔ C. Ensure financial security for Mine Closure
D. Pay royalty


These questions are based on the Mining Plan & Mine Closure Guidelines for Coal and Lignite Mines, 2025 and the provisions relating to Mine Closure Plans and Escrow Account.

Comments

  1. Looking for a reliable Dell Dealer in India for business and professional IT solutions? SanSo Networks Private Limited offers genuine Dell products with dependable support and expert assistance. Choose SanSo Networks Private Limited for trusted Dell solutions tailored to your business requirements.

    ReplyDelete

Post a Comment

Popular posts from this blog

INDIAN MINING & CONSTRUCTION EQUIPMENT INDUSTRY

Coal Mining Technology, Mining machinery, Coal By Products, CIL Performance

GENERAL MCQ ABOUT CIL